HomeProjectsA13 resurfacing

A13 resurfacing

A13 near Barking

VolkerHighways completed a total of 8,400m2 of resurfacing works in six areas along the A13 near Barking, on behalf of RMS.

The project was priced, mobilised and completed within three weeks. In addition, thanks to VolkerHighways’ high-quality delivery, while on site, RMS asked the business to carry out additional works, and the team completed a further 350m2 of patching. This reduced the cost of remobilisation and traffic management set-up, providing better value for money for the client.

  • Works included Movers Lane west bound off slip where 40mm of existing surface was planed off due to the surface rutting and a loss of texture, and replaced with specialised low carbon stone mastic asphalt
  • Laid 2,500m2 of new surface along the main dual carriageway, between Wennington Interchange and Ferry Lane Interchange
  • Resurfaced the Ferry Lane on slip and off slip and Commercial Road near Limehouse Link.

Facts and figures

  • Client
    RMS
  • Duration
    Three weeks
  • Project categories
    Surfacing
+